University of Exeter South Cloisters
Educational Case Study
Conversion of student accommodation into administrative offices.
This comprised of the addition of a third story onto existing buildings together, a new entrance block, as well as refurbishment and over-cladding of the existing building.
The Project
Project Name
University of Exeter South Cloisters=
Location
Exeter
Sector
Education
End Purpose
University
The People
Client
University of Exeter
Architect
Grange Architects
Main Contractor
Midas Construction
Consulting Engineer
Aecom.
The Contract
Contract Value
£8m
Contract Length
52 Weeks
Contract Completion
March 2015
Total project Value